You can either type your schedule below in ganttdown format or paste your .gd file
Format Reference
Wrap your schedule in <task> and </task> tags. Each task is one line:
<task>
<task#> <name> <YYYY-MM-DD or dep#> <duration>
</task>
Field 1 Task number — dotted hierarchy e.g. 1 1.1 2.3
Field 2 Task name — everything between field 1 and field 3
Field 3 Start date (YYYY-MM-DD) OR dependency task number
Field 4 Duration in working days Mon–Fri
Rules
· Dates must be ISO 8601 (YYYY-MM-DD). Weekends are rejected.
· A dependent task starts the next working day after its dep finishes.
· Dependencies must be defined before the tasks that reference them.
· Weekends are skipped in duration and chart display.
· Lines beginning with // are comments. Blank lines are ignored.
· Everything outside the <task> block is ignored.
Example
<task>
1.0 Project Kickoff 2026-04-13 1
1.1 Requirements 2026-04-13 5
1.2 Design 1.1 5
2.1 Development 1.2 10
2.2 Testing 2.1 5
</task>